Q2 2025 Construction Update

At the end of June 2025, construction of the commercial production facility was over 90% complete, and the project was on schedule for first copper cathode production before the end of this year.  Over 900,000 project hours were worked with no reportable injuries or environmental incidents on the project to date.

  1. All the injection and recovery wells planned for startup have been drilled and constructed (June 2025).
  2. The substation was completed in July (June 2025).
  3. Electrowinning area is continuing to progress on schedule. Installation of the cell end bus bars, cathode stripping machine (pictured), FRP structural and grating are well under way (June 2025).