Florence Copper Construction Update

  1. The solvent extraction and electrowinning area is progressing on schedule with the focus on electrical, mechanical and piping installation. Electrowinning building erection is underway (January 2025)
  2. The substation is progressing with concrete work nearing completion (January 2025)
  3. At the end of January, fifty-eight wells were fully constructed (January 2025).