  1. Earthworks for the SX/EW plant site are nearing completion and pouring of the concrete foundations is well advanced.
  2. Two drill rigs and a development rig working on production wells. At the end of June, 18 production wells had been completed and a third drill rig is now operating at site.
  3. Pond 3, which will be completed in August, provides the site with added water management flexibility.
  4. Producing gravel on site (using portable crusher) has provided significant cost savings.