Q1 2025 Construction Update

Construction continues to advance on schedule and first copper production is still targeted before the end of 2025. Overall project completion was at 78% as of March 31, 2025. During the first quarter there were approximately 440 contract personnel on site and 230,000 project hours were worked. Total project hours to-date are roughly 670,000 and there have been no reportable injuries or environmental incidents.

Summary of key activities in the first quarter:

  1. Electrowinning building structure is complete, except for the final roof and wall sections that will be installed after the electrowinning overhead crane is placed (March 2025)
  2. Installation of the cathode stripping machine commenced (March 2025)
  3. Electrowinning scrubber was installed (March 2025)
  4. Substation area has progressed with above-ground conductors, supports, and major equipment setting well advanced (March 2025)