Florence Copper Construction Update

As of August 2025, all areas continue to advance through the completion of construction and handover to the commissioning process.

  1. Construction of the west branch corridor in the wellfield advanced with completion of the liner, setting all skids, and commencement of pipe installation (July 2025).
  2. Plant site paving commenced (August 2025).
  3. The east branch corridor in the wellfield advanced into the commissioning phase. Construction of the west branch is nearing completion (August 2025).
  4. Construction of the site entrance began with underground electrical conduit and foundations started (August 2025).