October 2/07 -- Assembly of the SAG mill 28 KB, approx. 6 seconds at 56.6Kbps |
|
October 1/07 -- Assembly of the SAG mill 34 KB, approx. 7 seconds at 56.6Kbps |
|
September 27/07 -- Assembly of the SAG mill 30 KB, approx. 7 seconds at 56.6Kbps |
|
September 14/07 -- Arrival of the SAG mill components to Gibraltar 32 KB, approx. 7 seconds at 56.6Kbps |
|
August 21 - Five new copper cleaner float cells, in the process of being installed 17 KB, approx. 4 seconds at 56.6Kbps |
|
August 21 - Construction of high angle conveyor belt which will feed ore to the SAG mill, fine ore bin in the background 14 KB, approx. 4 seconds at 56.6Kbps |
|
August 15 - The SAG mill shells, loaded and departing Europe for Montreal. 23 KB, approx. 5 seconds at 56.6Kbps |
|
August 13 - Inside the SAG mill facility, preparations for the SAG mill installation are well underway 51 KB, approx. 10 seconds at 56.6Kbps |
|
August 13 - The SAG mill shells, at the Port in Europe being prepared for loading 47 KB, approx. 10 seconds at 56.6Kbps |
|
August 5 - Key SAG mill component, the ring gear, loaded in the hold, ready for shipping from Europe 51 KB, approx. 11 seconds at 56.6Kbps |
|
July 31 - Installing the trunions that will support the SAG mill 71 KB, approx. 14 seconds at 56.6Kbps |
|
July 31 - The near complete SAG mill building 59 KB, approx. 12 seconds at 56.6Kbps |